Home and Garden Guidebook

How to Build a Low-Maintenance Garden Storage Shed From Steel Cladding

Completed dark green corrugated metal garden shed with light brown wooden door and horizontal black bar, on gravel surface with trees and plants surrounding it
© Eugene Brennan

Have you ever wanted to build your own garden shed? I always have and attempted my first one when I was about 10 years old, but abandoned the project because of lack of materials, skills and tools! Eventually, 40 years later, I got around to building a proper garden tool shed.

Although quite large, my workshop had become cluttered with garden tools, bikes and other miscellaneous stuff, and I needed more storage space. So it was time to build another shed specially for all this extra equipment. This article is a diary covering the details of construction and might help you if you are considering building something similar.

How Much Did It Cost to Build?

Total cost of materials including the concrete floor was €1500. This is equivalent to about $1800 or £1334 at 2022 exchange rates.

Power Tools Required For Constructing the Shed

I used a lot of power and hand tools and while some power tools were pretty much essential for speeding up work, you can make do. These were some of the ones I used:

  • Miter saw for cutting timber to length. It’s advisable to buy one of these.
  • SDS Power drill for boring timber and making holes in concrete for fixing bolts.
  • Angle grinder for cutting sheets of cladding
  • Circular saw for cutting and shaping roof timbers
  • Cordless drill for screwing cladding to timber
  • Halogen or LED worklights if you want to continue working in the evening when days start to get shorter.

You also need general hand tools such as

  • Handsaw for quick cuts
  • Hammer for nailing
  • Level for making sure concrete and the shed are level and plumb
  • Utility knife for cutting underlay
  • Drill bits
  • Rake, shovel, buckets for concreting
  • Measuring tape. 6 m (20 feet) is adequate unless your shed is very long.

Stage 1: Clearing the Site, August 2015

The old shed had long outlived its purpose. Built in the late 40s or early 50s by previous owners, it was a patch work of corrugated iron, flattened out oil barrels and scrap timber, probably sourced from the salvage yard of a local man who used to collect this sort of stuff from demolished buildings. The roof was peppered with pinholes from corrosion and had leaked for years, however no amount of silicon sealant would fix what were now gaping cavities.

Old dilapidated green corrugated iron shed with peeling paint, weathered wooden door with glass panes, overgrown vines, clothesline with laundry and fallen apples on gravel
Old, corrugated iron shed, in need of replacement.
© Eugene Brennan

I thought it wouldn’t take long to pull the structure down with a hammer and crowbar. However the builders had done a good job, using spiral shank nails to hold the corrugated sheets onto the timber frame. This is probably a lot more secure method of preventing sheet removal by burglars than using TEK screws.

Close-up of metal crowbar inserted under the edge of weathered green-painted corrugated iron sheeting showing dirt, moss and fasteners
Prying off corrugated iron sheets.
© Eugene Brennan
Hand holding a rusty spiral-shank nail with large flat washer against a grassy background
Spiral shank nail
© Eugene Brennan

Stage 2: A New Year, 2016 and Back to Work on the Project

Cold, wet weather and incessant rain during the autumn and winter of 2015, getting side tracked by other chores and duties and a series of personal events led to abandoning the project for the rest of the year. I eventually got back to clearing the rest of the shed in February. The corrugated iron was bedded down under the concrete floor and had to be prized out with spades, crowbars and cut with an angle grinder.

Person wearing bright yellow work glove using a crowbar to pry green-painted corrugated iron sheet from wooden base on dirt ground
Prying off corrugated iron sheets
© Eugene Brennan

Stage 3: Starting to Concrete

June 1st, 2016

The existing concrete floor was at two different levels. It was partially cracked also and didn’t have a vapour barrier which meant the air in the shed was always damp, with lots of condensation on the underside of the corrugated roof on cold mornings, which inevitably dripped down over everything. I decided to break up the cracked section of concrete which resulted in a large pile of rubble. I would also lay a new floor on top of the remaining concrete section, but make it thicker at the edges for structural strength. The new shed would be several feet longer and wider than the existing one. This resulted in having to excavate lots of soil which needed to be spread out over the garden, under trees, into hedges and basically anywhere I could find space.

Marking Out

I roughly marked out the corners of the shed with 1/2" (12 mm) rebar and marking paint. Firstly I hammered two pieces of rebar into the ground to mark the front wall, knowing the length of the planned shed. Then I roughly positioned the 2 bars for the back wall knowing the width of the shed. Knowing the length and width of the shed and using Pythagoras’s Theorem, this gave me a measurement for what the diagonal length should be between opposite corners. This established the footprint for the shed.

Stage 4: Dealing With a Particularly Temperamental Cement Mixer

The Belle mixer had been thrown out but rescued several years ago from a scrap yard. It was minus a stand so I built a new tripod out of 1 1/2 inch gun barrel, 2 inch box, a short piece of round solid bar and some flat steel. It didn’t have an engine either. Modern Belle mixers are usually driven by a Honda or Robin engine but I decided to use the engine from my old Suffolk Punch cylinder lawn mower as a replacement. But little did I know what hardship was ahead of me! The float bowl on these engines tend to drip eventually, but because the engine was mounted at a 45 degree angle on the drum, the bowl was never vertical, so the float never sealed properly. The result was lots of petrol drips during mixes. Next problem was the drive belt started slipping during a mix, with another mix ready in the wheel barrow and a third mix spread out on the ground! Very frustrating! Eventually the engine stopped working and refused to crank. I opened it up and discovered that the splasher on the crankshaft had broken off. So the engine was running dry with no lubrication. This damaged the connecting rod and smeared aluminium over the crank shaft. I made a new splasher, but eventually when the concrete floor was almost complete, a large bang signalled that my ‘trustworthy’ engine had definitely reached the end of its life this time. A post mortem revealed that the connecting rod had broken up into 5 pieces. The last section of concrete had to be mixed by hand.

Old red Belle cement mixer with large drum mounted on homemade red metal tripod stand with wheels, petrol can on top, outdoors near wooden door
My Belle cement mixer with homemade tripod.
© Eugene Brennan

Stage 5: Building the Formwork and Laying Concrete

Building the Formwork

I decided to lay concrete in six sections. I used two-by-fours (2 x 4) for the form work (the timber “shuttering” or mould into which concrete would be poured). This shutter consisted simply of a rectangle, nailed at the 4 corners. For the long walls, 2 x 4 had to be joined with short 2 x 4 scraps because the lumber wasn’t long enough to extend the full length of the side. At the corners, nails weren’t driven home so that the formwork could be easily disassembled later with a crowbar without damaging the concrete it surrounded. Thinner boards can be used instead of 2 x 4, but 2 inch thick timber requires less pegs to hold it in place because it doesn’t flex and bow as much over a long span.

What’s a two by four?

A two-by-four, (2 x 4) or four-by-2 in the UK (4 x 2) is a piece of rough, unplaned lumber (wood or timber) with a cross-sectional area of approximately 2 inches x 4 inches (also written as 2" x 4", the quotes meaning inches). Typically these are available in lengths from 4 feet to over 20 feet long. It’s a popular size, used for constructing stud walls (framing), bench frames and other general construction. In countries that use the metric system, these are sometimes a bit thinner than 2 inches. (44mm by 100mm).

Getting the Formwork Square

With the formwork constructed in place and two rebar pegs hammered into the ground to mark the endpoints of the front wall of the shed, I dragged the frame into position so that its two end corners coincided with these pegs. Then knowing the width and length of the shed, I was able to calculate what the diagonal lengths should be using Pythagoras’ Theorem. Using two tapes stretched between opposite corners of the formwork, I altered its shape until the diagonals were equal. This is pretty much essential if you want the footprint of your shed to be rectangular and not skewed. If you don’t do this, you’ll run into problems later with everything off square and for example, roof sheeting will be crooked. I then hammered rebar into the ground to mark the two back corners and tied the four corners of the frame to the four pieces of rebar. Next I hammered pieces of 2 x 1 at 6 foot intervals into the ground and after levelling the formwork, nailed it to these pieces. This prevented any sideways or up and down movement.

Line diagram of a rectangle with length L and width W showing crossed diagonals and the formula square root of L squared plus W squared
Use Pythagoras' Theorem to calculate the length of the diagonals.
© Eugene Brennan

Laying Concrete

I had kept the existing floor from the original shed and used this as foundation. However if you intend to lay a floor, you need at least 4 inches of sub-base rubble to act as a foundation, topped with sand to stop the stones piercing the moisture barrier plastic. The ground is dug out beforehand so that this sub base is flush with the ground. 4" (100 mm) of concrete is plenty strong for a garden shed with no vehicular traffic, but 6" (150 mm) is the minimum for concrete that is going to be driven on.
1200 gauge polythene sheeting was used under the concrete as a moisture barrier. This makes for a really dry shed. If you don’t use a damp proof barrier, moisture rises through concrete and on a frosty day it can condense on everything. The floor was constructed in six, 1m (approx 39") wide strips.

Wooden formwork on gravel containing black plastic moisture barrier with first section of wet concrete poured at one end
Formwork in place and first slab of concrete laid.
© Eugene Brennan
Freshly poured rectangular concrete floor slab with wooden formwork edges and black plastic sheeting visible on one side
New slab of concrete
© Eugene Brennan
Completed concrete floor of the shed with wooden wall framing starting on the left and a blue metal stand holding a level
New concrete floor in place
© Eugene Brennan

Stage 6: Erecting the First Wall

Walls were constructed from 2 x 4s. Treated 2 x 4s were used for the bottom plates in contact with the concrete. I nailed on 4" damp proof membrane with galvanized slab nails to give the timber additional protection from rising damp. It’s recommended that studs are spaced 16" (40cm) apart for sturdy construction. 4" (100mm) round wire nails were used for nailing the studs to the top and bottom wall plates, a pair for each stud, top and bottom.

Wooden stud wall frame laid out on the concrete base with multiple vertical studs and horizontal plates in outdoor setting
First stud wall constructed.
© Eugene Brennan
Close-up of bottom timber plate of stud wall with black damp-proof membrane nailed underneath resting on concrete foundation edge
Damp proof membrane was nailed to the underside of the treated timber as added protection against wet rot.
© Eugene Brennan
First wooden stud wall erected and braced with diagonal timber on the concrete slab in a garden setting
First stud wall erected.
© Eugene Brennan
Technical diagram of a stud wall showing labeled parts: cripple, window header, top plate, window sill, stud and bottom plate
Parts of a stud wall
Ahp378User:Trurl, CC BY-SA 3.0, via Wikimedia Commons
  1. Cripple
  2. Window header
  3. Top plate / upper wall plate
  4. Window sill
  5. Stud
  6. Bottom plate / sole plate / sill plate

Stage 7: Erecting a Second Wall

All work was done single handedly and while walls were not excessively heavy, some thought had to be put into rising them into place. Quick release clamps placed at strategic locations at arms reach allowed me to clamp on lengths of 2 x 4s to act as stays to keep the walls in place. Once this was done, the stays could be nailed into place to make them more secure.

Second stud wall erected and connected to the first with diagonal braces and a ladder visible in the background
Second stud wall in place
© Eugene Brennan

Stage 8: Four Walls in Place

Four walls erected and ready for top plates. Notice the 1 x 2 diagonal braces. These were added to keep everything square. Should have cut the overhanging apple tree first. Removal was a bit awkward to avoid demolishing the walls!

All four wooden stud walls erected forming the complete rectangular frame of the shed on the concrete base
All four stud walls in place
© Eugene Brennan
Large cut tree limb being lowered with blue ropes inside the shed frame resting on corrugated iron sheet
Lowering cut limbs from the overhanging apple tree.
© Eugene Brennan
Apple tree being trimmed with a silver ladder against it viewed through the unfinished timber shed frame against blue sky
Should have cut this apple tree before construction!
© Eugene Brennan
Exterior view of the timber shed frame partially obscured by green plants and a bag of wood in the foreground
Tree trimmed back
© Eugene Brennan

Stage 9: Adding the Roof

Once the top plates were in place, it was time to build the roof. On advice from carpenters on a building forum, I decided to use 2 x 7s for rafters. Snow load can potentially amount to tons of weight on a roof. Birdsmouths were cut using a circular saw and reciprocating saw and waste chopped out with a chisel. Rafters were then toe nailed to the top plate at the front and back walls. Toe nailing means skewing the nails or hammering them at an angle so they’re less likely to pull out.

Close-up of the corner joint where top plate meets vertical stud on the timber frame
Two plates added.
© Eugene Brennan

Birdsmouths or notches had to be cut out of the ends of the rafters to allow them to rest on the top plates.

Person using a green Hitachi circular saw to cut a timber beam on a wooden workbench outdoors
Cutting birdsmouths.
© Eugene Brennan
Person using a green Hitachi reciprocating saw to cut a timber piece held on the gravel ground
Cutting birdsmouths.
© Eugene Brennan
Hands using a wood chisel and black mallet to chop out waste from a birdsmouth notch on a timber rafter
Chopping out the waste of the birdsmouths.
© Eugene Brennan
Rafters installed across the top of the shed frame with a silver ladder leaning against the structure
Rafters in place. These were nailed to the top plate and also tied using steel band.
© Eugene Brennan
Looking upward at the installed rafters and top plates of the shed frame against a blue sky
Rafters in place
© Eugene Brennan

Side view of the completed roof framing with rafters and top plates, ladder leaning on the right
Rafters in place
© Eugene Brennan
The rafters were later more securely attached to the top plate and studs with “Galvoband”, perforated metal strapping. These act as ties, potentially stopping the roof being lifted off the walls during a storm.

Stage 10: Adding the Fascias

I decided to use 2 x 7s for the fascias. Stronger, more chunky and less likely to warp than 1" boards. Before nailing fascias onto the ends of the rafters, I treated the latter with creosote substitute as a preservative. The fascias were nailed with galvanised 4" nails. Blocking (nogging) was used on the end walls for spacing the fascia. Quick release clamps held the boards in place until they were nailed.

Close-up of timber joints and clamps holding rafter and fascia members in place during construction
Adding 2 x 7s to act as fascias.
© Eugene Brennan
Completed roof framing showing top plates and rafters from a low angle
Fascias in place.
© Eugene Brennan
Full exterior view of the timber-framed shed with roof structure complete before cladding
Fascias in place.
© Eugene Brennan

If you plan to cut a lot of lumber, one of these miter saws is practically essential. (British English spelling “mitre”). This 12" Dewalt sliding compound miter saw (model DWS780) will do everything you need. It’s a corded power saw with a 120 volt, 15 amp motor and is suitable for cutting rough or planed lumber up 2 x 14 at 90 degrees

Yellow and silver DeWalt sliding compound miter saw shown in studio product photograph
DeWalt corded mitre saw. Image courtesy Amazon store.
© Eugene Brennan

Stage 11: Bracing the End Walls

Strong winds always blow from the south west and these would hit the front walls. I braced both short end walls with a “V” layout of 2 x 4s meeting at the ground and bolted to the corners of the walls.

Nighttime interior of the framed shed illuminated by work lights with a miter saw on a stand
Bracing the end walls.
© Eugene Brennan

Stage 12: Adding Underlay to the Roof

I sourced a permeable membrane from Screwfix.com to act as an underlay under the steel cladding. Smooth, cold surfaces attract condensation. The underlay catches any condensation drips from under the sheets, carrying it to gutters. Also its underside has a rough woven texture, so water vapour in air landing on the underlay doesn’t condense. Without this, on a frosty day, the underside of un-insulated steel cladding can get covered with condensation which ends up dripping over everything.

Person kneeling on gravel measuring a roll of black Protect A1 roofing underlay membrane with a yellow tape measure
Cutting polypropylene underlay membrane for the roof.
© Eugene Brennan
Underside view of the roof showing black underlay membrane fixed to the timber rafters
Underlay in place under the cladded roof. This stops condensation and drips during frosty weather.
© Eugene Brennan

Stage 13: Cladding the Roof and Walls

Once the roof was covered with underlay, it was sheeted with powder coated, square profile, galvanised steel cladding. This is really supposed to be fixed to laths nailed or screwed to the roof/walls, however I fixed it directly. This sheeting material is inexpensive and easy to work with. It can be cut with a thin disk on an angle grinder or air shears.

Sheet Fasteners

Sheeting was secured using TEK screws. These are hard steel screws with a coarse thread and a tip than can bore through sheeting without the necessity of pre-drilling holes. To use them, you make a dent in the sheeting with a steel punch or masonry nail. This stops the tip of the screw slipping when drilling. These screws are available in various lengths with either Philips head, hex head or hex socket head. Hex head screws can be driven with either a matching 8mm socket and socket extension or a dedicated one-piece extension and socket that fits into a cordless drill. TEK screws are available for attaching cladding to timber or steel, the latter have finer threads.

Hand using a Bosch cordless drill to drive a screw into green metal cladding at the roof edge
Fixing cladding into place with TEK screws.
© Eugene Brennan
Close-up of a gold-colored TEK screw with washer and hex head held between fingers
TEK screw for attaching metal cladding to timber.
© Eugene Brennan
Person driving TEK screws into green corrugated metal cladding using a cordless drill guided by a red string line
Fixing cladding into place on the stud walls with TEK screws. A line helps to keep the screws centred on the studs and noggings (blocking) between them.
© Eugene Brennan
Partially clad green metal shed with open doorway revealing the timber frame inside
Nearly all the sheets in place on the front wall.
© Eugene Brennan

Stage 14: Adding a PVC Fascia

After giving the 2 x 7 timber fascia a couple of coats of wood preservative, I clad the timber with PVC fascia so it would mean one less painting job to do in the future!

Nearly finished green corrugated metal shed with white PVC fascia, open doorway and plywood sheets leaning against the walls
Nearly all the sheets in place on the front wall and PVC fascia fitted.
© Eugene Brennan

Stage 15: Constructing the Door

The door frame was constructed from 2" x 1" steel box and inlaid with all the waste 4 x 2 cut-offs from construction. Flat strips of steel top and bottom, inside and out kept the boards in place. These were tack welded at regularly spaced intervals so water could drain out between the welds. Angle section steel can of course can also be used to construct a frame although box results in a more rigid door.

Steel door frame lying on gravel with wooden planks being fitted into the lower section
Door constructed from 2 x 1 steel box and scrap 2-inch timber leftovers.
© Eugene Brennan

Stage 16: Making the Door Hinges

Hinges were made from scratch from 6mm x 40mm flat steel, steel tube and scrap round steel bar from my local steel fabrication company.

Handmade steel hinge with welded plate and tube held in a hand against grass
Hinges made from scrap iron bar and round tube.
© Eugene Brennan
Close-up of a clean weld bead joining the tube and plate of a handmade steel hinge
Closeup of weld on hinges
© Eugene Brennan
Three homemade steel hinges and hinge components laid out on a wooden board
Three hinges made and ready to be welded to door frame.
© Eugene Brennan

Stage 17: Hanging the Door, May 2017

Hanging the door was somewhat tricky. I reckoned it would be quite heavy (it eventually turned out to be 10 stone), so I decided to hang the frame first before inlaying all the 2 x 4 panelling. Two hinge hanger parts were bolted to the timber door jambs first, then the frame of the door was clamped onto the other parts of each hinge. The clamps were then adjusted so that the door was spaced properly in the opening with an even gap all round. Next I took the door down again and welded the two hinge parts to the frame. With everything rigid and not likely to move, I rehung the door onto the two hinges, bolted the third hinge on and took it down again and welded it.
After fully panelling the door, it was time to rehang for the final time. This was very awkward, because three hinges had to be aligned simultaneously so the hollow hinge parts on the frame could be dropped into place. Ropes were fixed to the top of the door for safety to restrain it from toppling as I worked on the ground to raise the door bit by bit onto blocks of wood. Once the hinges parts on the jamb and door frame were aligned horizontally and vertically, I was able to slide the door sideways and allow it to drop into place.

Wooden door being hung in the opening supported by ropes and blue clamps during installation
Hanging the door. Restraints added to stop it toppling. Completed door weighed 10 stone.
© Eugene Brennan
Hand using a ratchet wrench to tighten a hinge bolt on the wooden door frame
Bolting the hinges to the door jambs.
© Eugene Brennan
Close-up of a black-painted steel sliding bolt lock with protective box mounted on the wooden door
Sturdy bolt added to door, complete with box to protect lock from being cut.
© Eugene Brennan
Finished dark green corrugated metal garden shed with light brown wooden door and horizontal black bar on gravel
Finished shed.
© Eugene Brennan

Disclaimer

This article is accurate and true to the best of the author’s knowledge. Content is for informational or entertainment purposes only and does not substitute for personal counsel or professional advice in business, financial, legal, or technical matters. 

Power and hand tools can be dangerous. Read and understand all manuals before use and take reasonable precautions including wearing personal protection equipment (PPE) to prevent against injury.

© Eugene Brennan 2019